Progress Thursday 12th December 2019

Dear all,

The monsoon rains didn't help activities today and it can't have been too pleasant for the PW Gang down the line doing drainage work. I suppose at least they can see if it is working as it should be!

Down the yard, the Maintenance Team started the routine exam on bubblecar 55006.

The toilet block has progressed well this week with the new hot water boiler being installed which will supply hot water to all of the sinks in the building, including running the electrics to it. The sink basins have been installed in both the ladies and gents, with pipework being ran round the room for the ones in the gents.

Leigh