 A very busy day in many parts of the railway

Test customers were at Wirksworth
AMCO were recovering equipment from the Holloway Road site and footbridge
The VCT completed the fence at Shottle
The base layer of concrete was poured in the maintenance facility       
At times the traffic in the yard was intense 
  