Tuesday, 1 November 2016

Progress Tuesday 1st November 2016

Hi all

Although the temperature dropped significantly plenty of tasks were completed in Wirksworth yard and Balfour Beatty were calibrating their track vibration equipment at Wash Green.
Henry Ellison received it's boiler wash out and Cathryn now has connecting rods. The frame was craned onto the wheels yesterday
Much shunting was completed to replace all the vehicles in their correct positions after the Maintenance facility was cleared for the crane operation yesterday
The PWay team re sleepered a long crossing timber on the water crane point and commenced cutting the timbers for the second Shottle platform structure
55006 had it's green tinted fibreglass domes returned to their correct white colour

All for now

Mike