Thursday, 23 July 2015

Progress Thursday 23rd July 2015

Hi all
 
55006 decided it did not want to work the1015 to Duffield after working faultlessly yesterday evening on vegetation clearance. Iris was quickly prepared and covered the service. 55006's  vacuum release valve was replaced and it worked the last three services. All departments recorded improved takings from yesterday.
The narrow  gauge steam engine was taken away having disgraced itself by not working any trains.
The DMU team repaired 55006 and prepared the three car for a Wedding train on Saturday
Dan keeps plodding on repairing the wobbly picnic tables but the public are certainly enjoying the additional seating on our platforms.
The EVRA SK received a coat of gloss to the east side
 
All for now
Mike Evans