Wednesday, 4 February 2015

Progress Wednesday 4th February 2015

Well not a bad day, pretty cold but plenty of winter sunshine. The Pway team finished the infamous P10 having relaid it in just 4 days. This most useful effort has been the latest in a series of relays in support of upcoming testing. Testing which may not have been able to take place if they hadn't helped out.

ARC conducted interviews again in the Pullman and much admin took place in preparation for train services starting on Tuesday.

The LMSCA continued working on the BSK as they prepare to lay the new floor in the brake compartment.

Leigh