Tuesday, 3 February 2015

Progress Tuesday 3rd Feb 2015

Despite the best efforts of the Met office we again had a most pleasant day.

P way continued with re timbering turnout P10 and after 3 days all is back together with ballasting and packing left to complete the job.

The Booking office had further business taking advance bookings and amongst other duties stuffing envelopes with the latest shareholders news letter.

LMSCA were busy again on the BSK.

Steam team continued with welding up and machining axle boxes, preparing Henry Hellison for a boiler exam and further work draw filing the rods off Cathryn to make them look pretty.

A lone worker at Duffield has been clearing off the rails on the RAPP ready for lifting, digging out and relaying about 6 inches lower to allow surfacing of the car park at a later date.

VCT were again out in force at mp 134 with 6 men warming themselves with 3 fires.

DMU team had much shunting preparing the trains for next weeks 3 days of public services.

Cheerybye.

MKT.