Tuesday, 13 August 2013

Progress Mon 12th August 2013.

Another earning day with a group taking over the coaching stock for the the day with a photo shoot adding money to our bank account.

P Way loaded all the spare rails, fittings and timbers laid around Wirksworth site left over from various jobs ready for tripping to Shottle. 4 bags of loco ash were used to fill some of the empty bays in the track at the North end of the yard reducing the risk of trips and falls when walking around trackside.

VCT had 2 fires at Idridgehay and carried out pointing repairs to the downside parapet wall on bridge 12 after damage from a falling tree during high winds last winter.

Weed killing team were out with the special weed killer for mares tail and managed to treat the whole line.

Buffet enjoyed much patronage from the photo shoot visitors and a few passing customers.

Rodney was again at Duffield attempting a repair to the ladies toilet water heater amongst other things.

MKT.