Thursday, 27 June 2013

Progress Wed 27th June 2013

PWT had yet another fair weather day today with 3 of the gang including our work experience chappy attending to a further 5 sleepers with the Land Rover whilst the rest of us continued with the framework for Wirksworth platform extension, the majority of which is now complete. Boarding for the surface arrives on the morrow.

Carriage cleaner spent the day cleaning the maroon set ready for stabling until required for the L&Y loco visit in July/August.

DMU team singular was busy painting the buffer beams on the 119 unit.

MKT.