All the timber for the extension of Wirksworth has been delivered today and P Way made a start on the project removing the fencing, gate and re setting the top copings to suit the new layout. All the timber has been moved to its respective place for construction to begin.

We were hosts to 70 plus guests on our mid day charter with the buffet very busy serving all of them luncheon after which they had a trip up the incline to round off their visit.

VCT were busy at FP 3 cutting out more overgrowth to open up the sight lines and managed 1 fire despite the interruption from train operations.

Rodney carried on with more weeding and general tidying at Duffield.