Wednesday, 23 September 2009

Wed 23rd Sept

Evenin' all,

Another busy day at Duffield, saw the completion of the new drainage
system through the wet bet and linking up to the ditch, to drain
surface water. A major achievement. A start was made on digging out the
Up Cess ready to realign the 'main line'. A few words to describe a
lot of effort.

Tomorrow sees Light engine leaving Wirksworth at 0900 returning
withthe works train in the afternoon, More work at Duffiels starting at
0800 with much digging out, de sleepering and a start on sluing.

Interesting fact - more people have recently been complaining of the
webcams and spiders, than actually turned up to do any work on one of
our biggest projects!
Phil


Internet Security tips and offers from Tiscali - http://www.tiscali.co.uk/security
_______________________________________________________________________