Evenin' all,

The story of two level crossings. Firstly, Gorsey Bank had its metal
grills fitted and now awaits its final painting, and the fitting of the
red circles. At Idridgehay, the posts for that level crossing were
transported to site and fitted.

Completion of the droppiong of bottom stone for the Narrow Gauge line,
as well as rough levelling.

More removal of scrap Buffer stops and bits, a general tidying of
site.

'Nottingham Castle' continues to take shape, ready for Santa to visit
in a few weeks time, bookings are coming in thick and fast.

Despite the heavy rain in the afternoon, the Per way team had a tidy
up session of the tool van.

Tomorrow sees a return to fishplate greasing - weather permitting.