Finally a beautiful sunny warm day which improves ones mood. The Tannery Team were in full flow today and are doing a great job. For those who haven't been following, the former Tannery building's mezzanine floor is being converted into a new Booking Office at Wirksworth as the current portakabin has seen better days. So far they have overboarded the previously lumpy bumpy floor and have now started to build a stud partition at the edge of the mezzanine. Today's photo shows this progress.

The buffet had a bit of work done in the kitchen today too.

Marsden Enterprises began his task of servicing and sprucing up one of the road/rail Land Rovers. A filter change is a good start. This is a most useful machine especially to support test work.

The contractor continued building the new wall in the car park too.