Monday, 17 November 2014

Progress Monday 17th November 2014

Dear all,

The main thrust of activity today was on the slip relay project in the yard. A small Permanent Way team worked their socks off today screwing the track down largely by hand as hired in mechanical assistance didn't arrive. A day of packing and levelling tomorrow, followed by connecting the levers, should hopefully see this project conclude late Wednesday (with a fair wind). They're off for a soak!

The Booking Office continued to process a steady stream of Santa bookings with some of the trains getting tight. The website shows the status of each train, with two yellow and one red at this moment in time. Another is about to go yellow shortly.

The LMSCA continued work on the rear end rebuild of the Mark 1 BSK also.

Leigh