Thursday, 9 October 2014

Progress Thursday 9th October 2014

Dear all
 
Another dank, wet and dull day where the planned roof sandblasting had to be called off in the hope that progress can be made tomorrow. The PWT concentrated on removing spare material from the relay of No 1 Road and travelled to Duffield to deal with debris that had fouled the line after last night's mini tornado. Very useful as the line was obstructed in many places.
 
The dmu team had another day shunting stock to allow for various vehicles to be in place for winter maintenance and modification.
 
The Booking Hall continued to process on line bookings that seem to bode well for the Jazz train and Santa.
 
Martin
 
Another couple of videos from across the pond!
 
http://youtu.be/N6JdcuOfBZw - Metra trains with two angles
 
http://youtu.be/mCgIbLorxbw - more electric trains and the interior of a long established station