Wednesday, 30 January 2013

Progress Wed 30th Jan 2013.

What a difference a week makes with last week a polar bears paradise and this week a proverbial sun kist Wirksworth. Much work carried out today by p way with a full line patrol and the 3 monthly ground frame lube, inspection and fpl check completed on our 7 ground frames.

Shottle platform builders were in their element in the fine weather with the south ramp completed and 50 feet of the next bottom course built on the concrete laid yesterday. More deliveries of sand, gravel and cement also received today at vast expense.

Booking office and buffet both open for business as usual and hopefully we might get some trains running this weekend providing mother nature remembers we aren't inside the Arctic circle.

Oh, and joy of joy the Komatsus' computer having had it's batteries disconnected for a week has rebooted itself and is now working normally presumably under expectation of permanent termination having had it's power supply annexed for a week - if it plays up again- Asta la vista baby (perhaps not the correct spelling but you get my drift.)
Computer nil - big hammer one.

MKT.

__._,_.___
Reply via web post
Reply to sender
Reply to group
Start a New Topic
Messages in this topic (1)
Recent Activity:
New Members 1
Visit Your Group
JOIN SHARESAVE!

Becoming a shareholder of WyvernRail has just become easier!  Join ShareSave and invest in your railway for just 10 Pounds a month.

See www.e-v-r.com/ShareSave for details.
Switch to: Text-Only, Daily Digest • Unsubscribe • Terms of Use • Send us Feedback
.

__,_._,___