Wednesday, 31 October 2007

Progress Report Wednesday 31st October 2007

Evenin' all,

Lots of activity again in the warm autumn sunshine, Running North to
South, the activity was more or less as follows:-

Roy and Les rendered the intercepter tank and started making the cover
for it; more green paint was applied to the Incline coach,

The narrow gauge team seemed to have Plant zooming around with
sleepers, rails and stone going in all directions.

More work was carried out on the new Trap Point protecting the main
line through platform 2.

Some members of the per way team continued to regulate the ballast
between Wash Green and the Hannages Footcrossing, the result is most
pleasing. Other members gave the pointwork a touch of lubrication, a
dirty job, but one that is done every few months. Hylton took stock of
requirements for the big attack on Fishplate greasing and bolting up.
This task will involve many hands over the next few months.

Paint was also applied to the Idridgehay Gate posts as well as the
home for the Power station.

At Idridgehay, the concrete for the crossing gates was delivered and
is now going off with the bolts for the gate posts cast in place.

We welcomed a new customer, who brought a special trolley for testing,
they also invited representatives from London Fire service, Network
Rail, CTRL, London Ambulance to see the emergency vehicle in action.
No photos are being published at this time, but the vehicle with six
burly chaps standing up ran to Duffield and back - such was the speed
and battery life, we also proved that the lighting was working
properly! Representatives from Derbyshire Fire and Rescue were also in
attendance. I firmly believe that further new business will result.

A busy day all round

Phil

__________________________________________________
Exclusive discounts on Norton Security from Tiscali http://www.tiscali.co.uk/products/securepc/

Special Events 2008 now online!

As the official website of the Ecclesbourne Valley Railway, we are proud to bring you the new 2008 Special Events information first!

Usually, we wouldn't make such a fuss over the events calendar, but this coming year contains arguably the most important event in our short history - the opening of the line between Wirksworth and Idridgehay. This is the start of the big break out of the Wirksworth area.

Whilst full details of this event will be released in due course, the dates are pencilled in there for you to browse! As it is likely to be busy that weekend, travel on the train must be pre-booked and details of how to pre-book your journey will be released shortly.

To view the events for 2008, please use the "Ticketing and Trains" link at the top, followed by "Events 2008".

Thanks,

Leigh

Tuesday, 30 October 2007

Tues 30th Oct

Evenin' all,

Once again, multi tasking was the order of the day. Some sleepers were
taken up to the site of the Intercepter drain, by the Maintenance
area.

Per way split into two teams, one made a start sorting out the ballast
dropped by Wash Green yesterday, whilst the other half was at
Idridgehay completeing the form work ready for the concrete for the
crossing gates.

The VCT were busy near Gorsey Bank, working in the Up Cess, clearing
the brambles etc., away from the new sign etc as well as clearing the
Up walkway.

In the Car park much was achieved on the Narrow Gauge line with much
ballasting, cutting of sleepers and people wandering about with lengths
of rail under their arm!. Opposite them the Logging department prepared
more bags of firewood.

Two machines were on site for Testing, they were Unimog based water
bowsers, which also doubled up as towing vehicles when the situation
develops.

The Pasenger Dept had a stocktaking day and also had several visitors.

Tomorrow sees another company testing their vehicle, they are bringing
several people to 'give it the once over'. More ballast fettling on the
Hannages, as well as concreting .

One unusual request came this afternoon, from the local constabulary
- some tables previouly stolen from the Town Hall were located in the
Hannages Brook, the best way to recover them was to convey them back to
base by rail, where they were collected by the Council.

Phil

__________________________________________________
Exclusive discounts on Norton Security from Tiscali http://www.tiscali.co.uk/products/securepc/

Monday, 29 October 2007

Monday 29th October 2007

Dear all
 
Again, a day of great activity with the late running of today's customer giving us the opportunity to put some ballast down on the Wash Green to Gorsey Bank section and then dribble what was left along the stretch opposite Bournebrook Avenue. Whilst the standard gauge was being ballasted a team were also ballasting the narrow gauge with an assortment of equipment including a mini digger, dumper and fearsome wacker plate.
 
Roy(71) and Les(77) together with Chris (21?) made steady progress with the interceptor pit and we welcomed a visitor from the Aln Valley Railway who may purchase our redundant Permaquip fleet. Further preparation of the Idridgehay gate posts was undertaken.
 
The Booking Hall was kept busy with our visitors and the usual phone calls.
 
Regards
 
Martin

Saturday, 27 October 2007

Progress Report Saturday 27th October 2007

Dear all,

A pleasantly busy day on a selection of fronts. The engineering dept
proceeded with the rectification of Sir Peter's injector pump and also
dealt with cleaning of the fuel filter system and on the class 31 the
air side of the radiators also continued to receive their bicentennial
cleaning.

Adjacent to the shed road the blockwork was completed on the new
interceptor pit as far as ground level and is now ready for the
re-inforcing concrete to arrive next week. Please do not pump out the
pit until the interceptor is finished.

A multitude of volunteers were seen to be at work around the children's
area, where the ramp has been stoned and also around the narrow gauge,
where ballast was being applied to the section of track in hand. The
ramped part of retaining wall of the Baileycroft dock has also been
cleared to show it off as a feature.

A steady day's business was done by the Ravenstor Line and the traincrew
also attended to the cleaning of the Trailer Car, an attractive task
which can be continued tomorrow, the luggage racks are always a nice
place to start.

If weather permits (the forecast is bad, however) the sleeper tops can
be cleared of mud around mileposts 139 and 140.

All the best, Anton

Friday, 26 October 2007

Friday 26th October 2007

Dear all
 
Our normal day for reflection and exploring the meaning of life was greatly disturbed by activity. Early bird boffins reviewed the infrastructure needed to restore and upgrade our web cam system and usefully ensured another early bird delivering materials to Roy (71) and Les (77) for the interceptor pit found them and their deep hole.
 
Special thanks to David Newby and Hylton who shunted the yard so we could accept three hopper wagons full of ballast, put Sir Peter where repairs could be effected, marshalled the ballast train for Monday and repositioned the Incline train ready for tomorrow.
 
The week's work for our hired in digger and driver finished with a clean up at Gorsey Bank and the preparation of walkways either side of the crossing. We have been very pleased with the productivity of this machine and driver and will certainly use them again in the future.
 
Roy (71) and Les (77) completed the concrete base of the interceptor pit and are ready for the next part of the plot. The children's play area work continued and the Booking Hall welcomed a number of visitors who were entertained by the ballast being tipped in from the Wash Green dock (repeating history).A young offender and supervisor made sterling inroads into platform cleanliness and the area around the Training Room.
 
The icing on the cake was a very late booking from a customer who was with us this afternoon nearly generating enough income to pay for today's stone delivery.
 
All in all, a satisfactory day.
 
Regards
 
Martin

Thursday, 25 October 2007

Thursday 25th October 2007

Dear all
 
A day of steady achievement with further green paint applied to the Incline dmu and more energy expended on the children's play area. Stone was delivered for the narrow gauge and the site of the oil separator pit grew ever larger reaching the footings of the old engine shed.
 
The Idridgehay gate posts were drilled ready for delivery to site and the VCT had a stock take of their timber stone removing many nails for our scrap drive. The Ravenstor service operated with modest success and the Booking Hall welcomed passengers and visitors.
 
The permanent way team ventured to Duffield to commence repairs to the tight curve into the station that has been causing concern. The gauge tie bars that we recently purchased have proved of great help in this process. Our mini digger driver continued with ditch digging in the Callow Park area to great effect and it was at the end of the day the excitement commenced. Sir Peter expired with the works train a little way north of Idridgehay. The works train contained the vehicle that would return the digger to Wirksworth ready for its activities at Gorsey Bank tomorrow.
 
A classic rescue was mounted with the staff returned by road to Wirksworth and the rescue train conducted to the failure in the approved manner. Protection of the failed train was provided and the whole consist proceeded north to collect the digger and the process into the car park to permit the digger to be unloaded. As darkness had descended the whole combined train was berthed in the car park overnight to be sorted tomorrow.
 
We have 60 tonnes of ballast being delivered tomorrow so will need to reorganise ourselves to cope with this and restore the Incline train to its position for Saturday.
 
A very good effort by all concerned.
 
Regards
 
Martin

Wednesday, 24 October 2007

Progress Report Wednesday 24th October 2007

Evenin' all,

A busy day with, not 1, not even 2 but 3 revenue earing companies
gracing us with their prescence. This was additional to passenger
services and the Buffet car earning a few bob in the process. Tube
Lines had a couple of drivers carrying out Route Knowledge training on
the Gorsey Bank Line

The Per way team were busy at Idridgehay digging the post holes for
the new gates, the holes are now nearly ready for a some concrete.

Mary and Rod were busy in their playpen making more of the new kiddies
play area. We had the mini digger opening up one of the old drainage
ditches on the 'racing straight' by Alton Manor, thus releasing the
trapped water, work continues there tomorrow.

Another 0800 start to convey the digger driver to site, then some
gentle shunting and some sleeper repairs 'down south'. Also picking the
digger up on the return journey. Works train to depart around 0930 ish.

Phil

__________________________________________________
Exclusive discounts on Norton Security from Tiscali http://www.tiscali.co.uk/products/securepc/

Tuesday, 23 October 2007

Tues 23rd Oct

Evenin' all,

A lovely sunny autuminal day, with two main areas of activity. At
Wirksworth the Passenger services were kept fairly busy with Half Term
passengers, the Buffet Car was also open and once again proved to be
popular. Around the Maintenance area, Roy and Les continued work on the
Pit drainage system, whilst Dave Mee applied more green paint to the
Incline coach. The logging dept were also in full swing. Mick has now
completed the assembly of the Idridgehay level crossing gate posts.

The other main area of activity was at Idridgehay, Many tons of
material were shipped elsewhere to reinforce embankments. The area
opposite the platform has now been levelled off and is nearly ready for
the Gardening dept to move in. The VCT were working with Per way and
much brash was disposed of, the hedge line was also tidied up. Some
granite ballast was relocated and either side of the level crossing
area had a dressing. A start was made on levelling the spoil heaps.

Tomorrow sees a mini digger being transported to a site to start ditch
digging, and most manpower will be at Idridgehay, digging the holes for
the gate posts (travel by car please). Also some more testing work.
Passenger trains will also be in operation.

Phil

__________________________________________________
Exclusive discounts on Norton Security from Tiscali http://www.tiscali.co.uk/products/securepc/

Monday, 22 October 2007

Fw: Mon 22nd Oct

----Original Message----
From: pjtarry@tinyworld.co.uk
Date: 22/10/2007 17:06
To: <wirksworths_railway@yahoogroups.com>
Subj: Mon 22nd Oct

Evenin' all,

An 0800 start at Idridgehay has resulted in piles! The Cess opposite
the platform has been given a good clean and scrape. It appears that
anyone who has wanted to dump things over the years, has fly-tipped
at
Idridgehay. Ther is a mountain of material waiting to be relocated
tomorrow. The Up Safe Cess walkway, north of thr crossing has also
been
levelled and now awaits some Type 1 to be laid and wacked in.

Pat and Mike have been having a tidy up session after the successful
Model Railway weekend. Several visitors made their way to Wirksworth
station to have a look around.

Tomorrow we need an early start for the works train - to please be
at
Idridgehay by 0930 with Mermaid and empty green low Flatrol ( Please
ensure two wheelbarrows are also on board) There is a great deal of
Mermaid work to do, so as soon as the train crew are ready please
come
down. The VCT squad are also welcome to start tidying up the
hedgeline.

Phil

__________________________________________________
Exclusive discounts on Norton Security from Tiscali http://www.tiscali.
co.uk/products/securepc/

__________________________________________________
Exclusive discounts on Norton Security from Tiscali http://www.tiscali.co.uk/products/securepc/

Sunday, 21 October 2007

Fw: Sunday 21st October 2007

 
----- Original Message -----
Sent: Sunday, October 21, 2007 6:14 PM
Subject: Sunday 21st October 2007

Dear all
 
What a very pleasant day with the crowds filling our three platforms to enjoy the dmu fest! The sight of simultaneous departures and arrivals at Platforms 1 and 2 was something to behold. These events coupled with the Bubble Car arriving and departing from Platform 3 created an environment worthy of some of the major stations on the network in the 70s.
 
Many congratulations to everyone who made it all happen including the marshalling and shunting well into Saturday evening and an early start today. Also thanks are particularly due to Julie who did record business in the Buffet Car and Jamie, aided by the Youth Offending Team, who undertook that most unglamorous but essential job of packing the car park.
 
There was also a sizeable team manning the 3 locations of the Model Railway Exhibition and Mike and Pat Craft deserve a special mention for pulling the whole thing together after another 12 months of planning and negotiation. Yet again the town of Wirksworth is put well and truly on the map by the endeavours of the Railway.
 
All this effort engaged around 30 volunteers. including some pressed men and women, which again demonstrates the dedication of all involved and there was even an opportunity to tend to the drainage at 40 steps and fettle the radiators on the Class 31.
 
A very well done to everyone.
 
Regards
 
Martin

Saturday, 20 October 2007

Progress Report Saturday 20th October 2007

Dear all,

Another busy Model Railway Exhibition, with a range of interesting
layouts, has brought people to the town and the railway. Many thanks to
all who have helped at the venues, at the station and on the trains.

In other tasks, the shed area continued to be prepared its new stores
container, work was undertaken on the roof of 03 084, on the road-rail
vehicles and on the Gat Ex.

All the best,
Anton

Friday, 19 October 2007

Friday 19th October 2007

Dear all
 
A less frenetic day but with an earning opportunity! A regular customer developing and electric powered machine claimed further improvement as the vehicle travelled to Shottle and back without incident.
 
The Amber Valley Loco Group topped up Margaret-Ann with antifreeze and started to prepare the Maintenance Facility site for the arrival of a new stores container. The Incline dmu received further attention as the sun warmed the day up and there was a great deal of activity in Wirksworth town to prepare for the Model Railway Exhibition opening tomorrow.
 
The Booking Hall entertained quite a few visitors amongst which was a Railway Inspector paying a "social" visit. He commented on our standard of presentation and lamented that the railway he was involved with did not have the same approach!
 
Regards
 
Martin
 
Duty Managers for the weekend are Anton, Saturday and me, Sunday - surplus energies are required by Roy and Les at the Maintenance Facility

Thursday, 18 October 2007

Thursday 18th October 2007

Dear all
 
I am not sure whether there is enough cyberspace to report on today's doings! However, I will try - the VCT have had a day of good housekeeping with a panel of Midland Railway fencing recovered on Tuesday being reshaped for use on a bridge parapet. Their stores have been re-organised and surplus items disposed of. Galvanised chain that had disappeared from sight was uncovered and applied to the fence line at the base of the former dust dock to create a nice finishing touch.
 
The steps were replaced onto Helen-Louise and blocks moved to prepared for the creation of an interceptor between the pit and the site drainage system. This will continue the improvements in the Maintenance Facility area.
 
Two gate posts were fabricated for Idridgehay and a defective sleeper was changed at the site of the trap points on Road 2 to enable the ground frame installation to be completed. The works train was marshalled for its activities next week in support of further machine work at Idridgehay, on the "racing straight" and at Gorsey Bank. Providence prevailed with the availability of the "new" fork lift that was able to discharge quite a substantial capital investment in rail, sleepers (for the narrow gauge), chairs and gauge tie bars totalling over £3000.
 
The scrap gathered from the level crossing installations was sorted, cut and skipped where appropriate. The silent talking tunnel was restored to life and a potential new recruit given an insight into the likely tasks ahead. This recruit will be accompanied by a lady that may cause pacemaker batteries to need a recharge.
 
We were pleased to welcome a paying guest for testing and L53 was in action as part of the EMC evaluation for the vehicle. We were also happy to host Jonathan Webb from Rail Engineer, a loyal supporter of the enterprise, who was entertained by Mark Brooks from Tube Lines with the bonus of our other customer on site for an article about our commercial activities.
 
Regards
 
Martin
 
PS Many thanks to Neil and Leigh for bringing our web sites back to life - the new look is excellent!
 
 

Wednesday, 17 October 2007

Progress

Wednesday 17th October 2007
 
Dear all
 
Another day of great endeavour with L53 undertaking EMC testing on the TBTC track leaving the battery locomotive blinking in the autumn sunshine. The permanent way team completed all the new signage for Gorsey Bank with the exception of the Up fixed distant. They also recovered all the, now, redundant signs and scrap from the old installation. The drain south of Gorsey Bank crossing was unblocked following the various earthworks in the area and is flowing well amongst the white goods deposited outside our boundary there.
 
A mammoth move of sleepers from the Flatrol freed that vehicle for activities next week and lift plates were fitted to a particularly bad rail joint on the Hannages.
 
I forgot to mention yesterday that the gate hinges were fabricated for the Gorsey Bank gates and we await the road/rail machine and trailer that will transport them to site and assist in placing the gates into their final position.
 
The Passenger Services team assembled for a meeting to review their activities and the Booking Hall received a few visitors.
 
Regards
 
Martin

Tuesday, 16 October 2007

Progress

Dear all

Another day of activity on many fronts. The VCT were earning money for their next chain saw by undertaking a little contract work for the Tube Lines project to enable specialists to take sound and electro-magnetic interference measurements on the TBTC test track over the next two days.

Meanwhile, the permanent way team finalised the new signage at Idridgehay by fixing the Up distant signal board. Whilst at Idridgehay the team undertook some drainage work and ballasted either side of the crossing. After that work was complete the team moved to Gorsey Bank to remove redundant signage and treadles. They then turned their attention to the new signage with some put in place and the sites for the remainder identified.

The Booking Hall welcomed a possible new recruit to their team and the Mess Hall was restocked with the essentials of life. Geoff Adam's celebrated his birthday by the provision of a splendid Thomas cake.

The final touches were put to the Passenger Services budget for the next financial year after a great deal of background work by all concerned.

All in all, another great day.

Regards,

Martin

Monday, 15 October 2007

Progress

Dear all

A day of sorting the diesel multiple units out for the weekend and a little light maintenance on Faraday. We plan a dmu fest! on Sunday when all our services will be operated by dmus including the Incline. The 2 car Met-Cam will be operating non passenger demonstration runs from Platform 2.

Much admin and planning took place and the Booking Hall entertained a few visitors.

Regards

Martin

Sunday, 14 October 2007

Progress Report Sunday 14th October 2007

Dear all,


A pleasent on many fronts in terms of the passenger service a quietly profitable day,with a visit from the 18c club 41 in all with tea / coffee on the Gattex they all had a pleasent day.
Much interest in the Tube Lines battery engine.

Activity has been on several fronts during the day with a limited number of volunteer's.

Collected up clips, nylons and pads at foot of Incline and placed in new bags.
Track patrol yard and incline, knocking in Keys.
Cleared drains north of Idridgehay as far as outflowing culvert.

Further work carried out on 31



Thanks to all concerned.

J.Ball
Duty manager.

Saturday, 13 October 2007

Progress Report Saturday 13th October 2007

Dear all,

A day of some curiosities. We were not able to get to grips with the task of sorting PW materials, as today was a conscript free day.
However, much progress was had by engineering with work done on the Lister, on wire brushing and painting various parts of 03084 and on the ventilation system of the class 31.

In terms of the passenger service a quietly profitable day was had and in the intervals repairs were carried to the Booking Hall and some spring cleaning and lite gardening were done despite a damp start to the day.

At Duffield various material was reported to have been cleared, bagged and moved from the platform area and work done to tidy up the down slow platform and the general area of the compound, I do not doubt a full report will be made available presently.

In the afternoon the Penguin was returned having made a bid to escape at 1.00 am last night accompanied by an assortment of the Feckless who left it in the middle of North End while attempting to make off with a number of toupees from the hairdressers. The said Feckless were last seen heading up the M1 towards Sheffield, allegedly pursued by a bobby on a bicycle from Matlock. The Penguin has now been chained to the revetment wall of the Children's area using the largest chain in Christendom and tonight the footpath and main road gates are to be locked.

All the best,
Anton

Friday, 12 October 2007

Progress, Friday 12th October

Dear all

A pleasant day in the autumn sun allowing further painting of the Incline dmu coach. Progress was made on the enhancements to the children's play area and the road/rail lorry received attention to its electrics.

The Booking Hall welcomed a few visitors and the Buffet Car was prepared for the entertainment of a group on Sunday.

Idridgehay level crossing was reopened to road traffic and many congratulations are due to everyone involved in delivering this project on time and under budget! It has involved a great deal of work over the last fortnight and we won't have to do it again for another 30 years (I hope!).

Regards

Martin

Duty Managers for the weekend are Anton, Saturday and John Ball, Sunday - the key task being the rebagging of all the small permanent way materials resting alongside the Incline for transport to Shottle to enable the Maintenance Facility project to restart.

Thursday, 11 October 2007

Progress, Thursday 11th October

Dear all

Another day of sterling endeavour with all but one of the Idridgehay signs planted just leaving the Up fixed distant to do next week. All surplus posts and scrap have been moved from the Idridgehay site and much unwanted timber has been consigned to potash. Temporary blue fencing has been erected until such time as we install the crossing gates.

Back at base the trap point ground frame for Road 2 has been concreted in and various technical things attended to. (We do need to source an Annetts key - please check your loft/garage). The logging department was in production and some narrow gauge rail cut to length. More component recover took place from Wee Yorkie and the Booking Hall received a number of visitors.

There has been as pleasant surge in bookings for MyTestTrack over the next three weeks.

Regards

Martin

Wednesday, 10 October 2007

Progress, Wednesday 10th October

Evenin' all,

Two main activities involving two different departments. Firstly the Loco engineering section had the blue 03 in the Maintenance area and removed one of the connecting rods, which showed some wear, this was despatched to Butterley for machine work to be carried out on it. On the ajoining track more work was carried out on the Incline coach.

A visitor from Boston (US of A I believe) had a trip on the Incline train. He was so keen that he made a handsome contribution to costs.

The other main activity was once again at Idridgehay. All of the tarmac has been laid and rolled, due to the thickness it will take a good 24 hours plus to go off. The bi t- left - on - the - back - of
- me - wagon - sir, was dropped beside the track in the area which will become the staff car park (AKA Idridgehay Park and Ride). Most of the new fixed signal boards were planted along with speed boards, just the Up Fixed Distant and a speed board to be added there. The Treadles were removed carefully and all bits retained for storage. The works train made a welcome return to Wirksworth traversing the new level crossing several times during the day.The old signalpost that has been on the platform these many years was removed as well as the Up Home post. Many local residents from Idridgehay dropped in to see the progress.

The Wirksworth Tourist people held a meeting at the station, after which the Wirksworth Station Master paid a visit to the workers at Idridgehay.

More bodies required for tomorrow to erect the last of the Signals as well as recover redundant assets.

Phil

Tuesday, 9 October 2007

Progress, Tuesday 9th October

Evenin' all,

Due to heavy rain, no tarmacing took place at Idridgehay today, which now puts us a tad behind schedule. However the Clearance team braved the elements, continuing their endeavours in the area.

Per way took one of the firewood department down the line so that he could load up some logs to keep their department busy - big rush coming soon.

Per way also started the connection of the new Trap point for road 2 to the north of the Platform 2, This has now been positioned, the bench has been dug out and fixed, we now need to mix some concrete to hold the frame in place - very dirty and muddy, and yet such lovely fun!

The train was also loaded with signs ready for an early start to Idridgehay in the morning.

Phil

Monday, 8 October 2007

Progress, Monday 8th October 2007

Evenin' all,

The massed ranks of 4 turned up at Idridgehay, a few tons of stone were dropped in the Level Crossing hole, and was subsequently whackered. Sleepers were cut around the post holes, and more of the drain was filled in. Paul joined us after lunch and spent all afternoon cutting the sleepers to fit around the rails, to give the council something to tarmac up to in the morning.
Tomorrow sees more work at Idridgehay. Train leaves at 0915.

All remained quiet at Wirksworth, with a couple of visitors and the usual phone calls offering amazing services.

Phil

Sunday, 7 October 2007

A blog a day


Hi Neil,

OK, so here's the first foray into the Blogosphere, and just in case its a problem, I've put on my asbestos codpiece.

Anton

PRESS RELEASE: Countdown To The 2012 Olympics - MyTestTrack.com Helps Tube Lines Re-Signal for Olympic Success

FOR IMMMEDIATE RELEASE

MyTestTrack.com – a venture by WyvernRail plc

Countdown To The 2012 Olympics

MyTestTrack.com Helps Tube Lines Re-Signal for Olympic Success

Wirksworth, 7TH October 2007: Tube Lines’ battery-electric locomotive L53 has arrived at MyTestTrack.com’s facilities in Wirksworth to kick-off an 18-month testing programme that will be a part of leading Tube Lines, the company responsible for the maintenance and upgrade of all the infrastructure on the Jubilee, Northern and Piccadilly lines, to increase capacity to allow for faster, more frequent and reliable services to serve London and the 2012 Olympics.

The revolutionary transmission-based train control (TBTC) system uses train and track-based sensors to detect the location of trains with higher accuracy than existing methods, leading to reduced headways which, combined with lengthened trains, will lead to an increased capacity and a reduction in journey times.

Wirksworth was selected as a test site for engineers’ trains being equipped with the new system. The TBTC signalling system was installed on the Gorsey Bank passenger line during the spring of 2007. The TBTC system is being designed and manufactured by Thales Rail Signalling Solutions Ltd under contract to Tube Lines as part of a consortium which includes Halcrow, Tube Lines and LH Group Services.

“This is a key milestone in commissioning new signalling for London’s Underground and we are delighted to be working with WyvernRail to ensure the efficient testing of our fleet of engineers’ vehicles,” said Paul Weidlich, Tube Lines’ Project Manager on the TBTC programme. “WyvernRail’s close relationship with LH Group, who are fitting the equipment, combined with their growing reputation, has given us the confidence to undertake this element of testing in Derbyshire,” he added.

Phil Tarry, WyvernRail’s director responsible for MyTestTrack.com was delighted to welcome the first locomotive to Wirksworth. “This is a great day for us all. We have been preparing to support this testing programme for nearly eighteen months and we are proud to be playing such a crucial role in enhancing our capital’s network in time for the 2012 Olympics.”

LH Group received the first vehicle, a battery-electric locomotive, at their Barton-under-Needwood works in May 2007 for fitting of the vehicle on board computer. The locomotive has now moved to Wirksworth for signalling tests and will be followed by a number of other vehicles, such as tamping machines, Schöma diesel locomotives and more battery locomotives that will all be put through their paces on the new signalling system at the test track over the next eighteen months. The plan is for each vehicle to receive up to five days of testing although this may shorten as experience of testing vehicles increases. After satisfactory tests, the vehicles will return to London.

Tube Lines employees will be based at Wirksworth when tests are conducted, to drive the various vehicles and ensure the smooth running of the project. Thales, who under their contract to Tube Lines, design and build the TBTC equipment, will be operating the dedicated test equipment at the control centre for TBTC which has been established by Wash Green Bridge in Wirksworth.

Ends.

Note to Editors:

High-quality digital images are available to download at:

http://plc.wyvernrail.co.uk/files/DSC05925.JPG

Depicts locomotive L53 shortly after arrival at MyTestTrack.com’s facilities in Wirksworth, Derbyshire

http://www.tubelines.com/news/imagelibrary/Trains/train20.jpg

Depicts a Schöma Diesel locomotive of the type that will be tested in Wirksworth (Image courtesy of Tube Lines)

http://www.tubelines.com/news/imagelibrary/Trains/train2.jpg

Depicts a battery-electric locomotive of the type that will be tested in Wirksworth (Image courtesy of Tube Lines)

http://www.tubelines.com/news/imagelibrary/Trains/train3.jpg

Depicts a tamping train that will be tested in Wirksworth (Image courtesy of Tube Lines)

About MyTestTrack.com:

MyTestTrack.com is a venture by WyvernRail plc. WyvernRail is reopening the Ecclesbourne Valley Railway between Duffield and Wirksworth and, in a very short time, has transformed the line from a neglected wilderness to a clear route suitable for vehicle movements throughout its length. WyvernRail is locally owned and managed with an attitude to make things work.

MyTestTrack.com offers competitively-priced service that is available at short notice to railway engineering companies for testing and training. The company offers a single point of contact, including a dedicated rail industry hotline (0870 766 2098), and a range of facilities to suit requirements, whether they be at short notice or for the long term.

Full details can be obtained from http://www.mytesttrack.com/.

About Tube Lines

On 31 December 2002, Tube Lines assumed responsibility for the maintenance and upgrade of all the infrastructure on the Jubilee, Northern and Piccadilly lines as part of the largest improvement programme the Tube has ever seen. Together these lines carry 40% of Underground passengers. Tube Lines has a 30 year Public Private Partnership (PPP) contract with London Underground. The contract is output based, meaning Tube Lines is rewarded for good performance and penalised for poor performance.

Reversing the effects of decades of under-investment in the Tube is a huge task requiring an injection of resources on the scale of which the Underground has never seen before. Tube Lines is involved in a massive improvement programme, tripling investment and committing over £4.4 billion to improve the Jubilee, Northern and Piccadilly lines in the first 7½ years – the equivalent of spending almost £1.6 million per day.

Tube Lines is responsible for:

* Over 200 miles of track

* 255 trains

* 100 stations

* 2,395 bridges and structures

* 71 lifts

* 227 escalators

Saturday, 6 October 2007

Progress Report Saturday 6th October 2007

Dear all,

A day in which the priority tasks of shunting and step painting were completed before morning tea was taken. Following morning tea and a bag of fruit pastilles, the staff roused themselves to deal with the interior end screen painting of the platform 2 waiting shelter, and a coat of paint was also applied to part of the platform side of the Booking Hall. Engineers undertook work on the class 31 and 03 084, and D2158 has taken over passenger duties.

Clearance was undertaken south of Rowland's Crossing by the white van and egg sandwich department, and a hoodie, sorry, conscipt, was delegated to sweeping the whole of the Station Road gutter. The passenger service trundled happily backwards and forwards all day as did the till drawer. For those of you interested in the film show, there are only ten tickets left. Two new volunteers were welcomed and the magnificence of our endeavour was admired from as far afield as Australia.

The priority task for tomorrow is the tidying of the store area between the green trailer car and the Ravenstor line, where various items of small track materials need sorting and bagging properly, bags and sleepers stacking neatly and rubbish removing.

All the best,
Anton

Friday, 5 October 2007

HOLBY COMES NORTH

Top BBC Drama Places Wirksworth’s Railway in the Big League and RailFilmLocations.biz is launched to promote filming at the Ecclesbourne Valley Railway

Wirksworth, 29th September 2007: Wirksworth Station was upgraded to main line status and witnessed dramatic scenes and a lucky escape for characters in the BBC’s top medical drama ‘Casualty’ broadcast tonight.

Only months after taking centre stage in ITV’s thriller ‘Mobile’, the Ecclesbourne Valley Railway has again achieved top billing with the BBC as the scene of an explosive episode that was filmed in June.

Wirksworth station was transformed both in appearance and location, partially thorough the work of the BBC’s set designers but also through the efforts of the railway’s own volunteers who have built two new platforms at the station in just six months, allowing the station to take on the appearance of a through station on the main line.

The plot for the episode was under wraps until tonight’s broadcast, but the BBC were fulsome in their praise for the high standard of support provided by the railway’s volunteers and management.

The filming took place over three days and involved two trains and used scenes at several locations down the line. In addition to using the railway, the BBC crew employed extras from Antony Gell School, giving several pupils the opportunity to appear on the small screen.

“We are delighted to have brought Casualty to Wirksworth” remarked Phil Tarry, WyvernRail’s Projects Director. “Our modern rolling stock continues to attract the film and television industry; indeed since we began, our intercity train has appeared under the identities of two fictitious train operators and even German Federal Railways” he added.

The railway is now promoting its rail filming facilities under the banner RailFilmLocations.biz and this operates in parallel with the company’s highly successful MyTestTrack.com engineering business.

Ends.

Note to Editors:
Further information can be obtained from
www.RailFilmLocations.biz
The following images are available for reproduction:
http://www.railfilmlocations.biz/press/DSC05550.jpg
Depicts RailFilmLocations’ express train, as used in Casualty.

http://www.railfilmlocations.biz/press/IMG_0853.jpg
Depicts RailFilmLocations’ express train arriving at Wirksworth, masquerading as ‘Lightbourne’ for Casualty.

http://www.railfilmlocations.biz/press/PIC_0015.jpg
Depicts Wirksworth station dressed as ‘Lightbourne’ for the filming of Casualty.

http://www.railfilmlocations.biz/press/PIC_0064.jpg
Depicts the departure board used at Wirksworth for Casualty.

Progress, Friday 5th October 2007

Dear all,

A very peaceful day today after the excitements of the week. A little light baggage trolley painting was achieved, some oil purchased for Helen-Louise and stocks gathered for the evra stand at the Mickleover model railway exhibition.

The Booking Hall welcomed a number of visitors.

Regards
Martin

Duty Managers for the weekend are Steve for Saturday and Mike Evans Sunday. Jobs available include the application of non-slip paint to Tube Lines boarding steps south of Wash Green bridge.